In every carve-out I’ve worked on, there’s a moment when someone says, “Don’t worry, the TSA covers that.”
Sometimes it does. More often, it covers something close to that, written by people who were never going to be the ones relying on it.
A Transition Services Agreement is the document that keeps a divested business running on the seller’s systems until the buyer can stand up its own. On paper, it’s a schedule of services, durations, and fees. In practice, it’s where the seller’s incentives and the buyer’s needs collide, every week, until the last service is exited.
I’ve seen this from both sides of the table. At Ardent Health and SCL Health, I managed both the acquiring and the divesting activities for St. Francis Hospital and its 13 clinics. More recently, I led three of the five IT integration workstreams on a cross-border acquisition that turned a U.S.-only company into a global one: roughly 100 people across 20 countries, including China, India, and the Netherlands. Identity and end-user computing, network and infrastructure separation, and security and compliance were mine. All of them started out running on the seller’s systems.
The TSA you sign is the opening offer. The one you exit is the real agreement.
The Incentives Never Line Up
Let’s be honest about the two sides of the table.
The seller wants out. Every month of transition service costs them people, licenses, infrastructure, and attention that should be going to the business they’re keeping. A TSA is not a revenue line anyone at the seller is excited about. It’s a cost they’re trying to end.
The buyer needs stability. Users have to log in on Monday. Email has to flow. Engineers need their labs. Finance needs to close the month. None of that can stop just because the deal closed and the buyer’s own environment isn’t ready yet.
Neither side is wrong. But pretending their goals are aligned is where the trouble starts. Every ambiguous line in the TSA schedule gets read by each side in its own favor, and usually nobody notices until something the buyer depended on quietly stops working.
I watched this play out with an engineering private cloud. The seller ran one of the largest private clouds in existence, with more than a million vCPUs. Roughly 1,700 of them belonged to the business we were acquiring and had to be carved out into an environment of ours that didn’t exist yet.
About six weeks before day one, the seller decided we’d get three months. In that window we had to work out what engineering was actually using the capacity for and where it could legally be hosted. We also had to design the architecture from scratch and give least-privilege access to engineers in several regions, including contractors in China who needed to work with data covered by GDPR.
Three months was the seller’s number, not ours. So we made the problem smaller. We consolidated the environment in Europe, where most of engineering would be based, to keep the data where it needed to stay. Access from other regions, including China, would go through VDI. That became a single global access model, so we’d support one system instead of a patchwork. It was still in progress when I rolled off, but we had created a viable approach.
Discovery Is Where TSAs Are Won or Lost
Most TSA problems are really discovery problems that showed up late.
On the cross-border deal, writing the TSA specifications and working through application discovery and licensing were part of my scope. The gap between what the schedule listed and what people actually used is where most of the work lived:
- Identity. Every user’s account, MFA, and single sign-on lived in the seller’s directory. Nothing else moves until identity moves.
- Applications and licensing. Discovery meant finding every app, who used it, and whose license it ran under. Software covered by a seller’s enterprise agreement doesn’t transfer by default.
- Labs and engineering infrastructure. Physical and virtual labs had to be moved, and private cloud capacity for engineering had to be built in several countries.
- Data location. European users’ data had to stay in Europe, which shaped how the new Microsoft 365 tenant was set up.
- Physical space. Some locations needed new offices built out before anyone could move.
My rule is simple: if it isn’t in the schedule, assume you don’t have it.
The way I find the gaps isn’t by reading the agreement harder. It’s by following the work. Walk through a day in the life of an end user. Follow the login. Follow the data. Every place the trail crosses into the seller’s environment is a service, whether or not anyone wrote it down.
Here’s the one I won’t forget. The business shipped devices in the field that took over-the-air firmware updates. Every update had to be signed and validated through a certificate-based security service run by a third party. That service was essential and highly secure. And it wasn’t in the TSA schedule. Due diligence never called it out.
I raised it. The seller said they’d look into it, met internally, and went quiet. When they finally came back, it was dangerously close to day one.
The harder part was on our own side. One engineering director understood over-the-air updates and certificates. That part is fairly basic when you own the system from the start. What nobody had worked through was what it would take to transfer it: moving a live chain of trust from one company to another without breaking a single device in the field. That was the real problem. I’d been through this before: at Microsoft, I helped build Windows Update, one of the first large-scale over-the-air update systems. So I knew what it meant to lose control of the trust chain that tells a device an update is genuine.
That experience is what let me explain it to our executives and the integration lead in business terms. If this service lapses, we can’t update devices that customers already own. That made it a TSA item. It needed terms and an end date, not an open question.
The first negotiated win was modest. The seller agreed it belonged in a TSA, and the deadline moved from day one to TSA close. That bought time. It didn’t solve the problem, and the next part turned into a security negotiation of its own (more on that next week).
This is the same forensic approach I use for dependency mapping on any large program. In an M&A deal, it just comes with a contract attached.
The Exit Date Is a Dependency, Not a Deadline
Every TSA service line has an end date. Most teams treat that date like a finish line. It’s actually a dependency, and it sits on the critical path from day one.
For every service, I want four answers before the ink is dry:
- What replaces it, and who builds the replacement?
- What’s the real lead time, including procurement, licensing, and security review?
- What do we need from the seller to cut over: data exports, access, configuration details, people’s time?
- What happens if we’re not ready when the term ends?
That third question is the one that gets missed. Exiting a service usually requires the seller’s cooperation, and that cooperation is itself a service. If it isn’t in the schedule, you may find yourself negotiating for a mailbox export in month eleven with very little leverage.
On the cross-border deal, every service needed a disposition decision: transfer it, replace it, or retire it. Getting to that decision for each line, and getting the seller to agree to it, was a workstream of its own.
The exit is a cutover. Plan it like one, with rehearsals, rollback criteria, and a clear go/no-go.
Run It Like a Negotiation, Because It Is One
Once the TSA is signed, the negotiation doesn’t end. It just moves from the lawyers to the program team. Here’s how I manage it.
Keep a running service ledger. Every request outside the written scope gets logged, in both directions. When the buyer asks for “just one more thing” and the seller says yes, write it down. When the seller quietly reassigns the engineer who handled your tickets and response times slip, write that down too. Scope creep runs both ways, and the side with better records wins the conversation.
Ask for extensions early. Extensions get more expensive, and your leverage shrinks, the closer you get to the end date. Early on, the buyer has deal momentum and goodwill. Near the end, the seller holds the off switch. If you can see a service won’t be ready, raise it while you still have options.
Remember who’s on the other side. The people running your services at the seller are often watching their own roles wind down. They didn’t negotiate the deal, and they still answer your tickets. Treat them well. A good relationship makes the hard conversations easier. It doesn’t replace the tracking.
On the cross-border deal, I had a good working relationship with the seller’s integration owner. He was responsive, and that made a lot of things easier. Even so, there were areas where the seller’s side seemed to drag its feet. A good relationship doesn’t make those go away. What kept them moving was refusing to let them drop: every one stayed in tracking, sat on the risk register, and came up in every meeting until it was resolved.
What a TPM Actually Brings to a TSA
The lawyers write the agreement. Finance prices it. But the TPM is the one living inside it every day, translating between two organizations that want different things and need each other anyway.
That job is part discovery, part dependency management, part cutover planning, and part diplomacy. Done well, nobody notices the TSA at all. Services exit on time, users barely feel the change, and the deal delivers the value it was supposed to.
Done poorly, the TSA becomes the most expensive line item nobody budgeted for.
There’s one part of the TSA I left out on purpose: security and compliance. Who owns them while the systems are shared is a bigger question than it looks, so it gets its own post next week.
The TSA you sign is the opening offer. The one you exit is the real agreement.
Andrew Weinberg is a Principal Technical Program Manager with 25+ years in healthcare IT, enterprise infrastructure, SaaS, and M&A integration.